Critical path in PERT / CPM analysis. (Oct 2006)
Critical path indicates the path containing all critical activities. The critical path is the longest path in the network. All activities on the critical path have zero floats and zero tail and head slacks. For critical activities Earliest and Latest starting and finishing times are equal.