Events and activities in PERT & CPM. Â (Oct 2004)
Activities-
- Activities represent actions which are represented by Arrows.
- Activities consume resources and time.
- Every activity has a Tail event (start) and Head event (end).
- Activities can be critical or non critical. Critical activities represent critical path.
- Critical activities have zero floats.
Events –
- Events represent point of time. They are represented by Nodes or circles.
- Events do not consume any time or resource.
- An event represents start or end of an activity.
- An event may be critical or non critical. Critical events have zero slacks. Critical events connect critical activities.